A sign of new times
The PCI article on our new halls is available to read here.
The PCI article on our new halls is available to read here.
The new church halls were dedicated to the Glory of God by Rt. Rev. Dr. David Bruce, Moderator of the General Assembly, Sunday 9th May 2021. More Photos More photos can be found on...
Dear friends, It’s always good to have an excuse for a celebration. God’s people in the Old Testament made quite a festivity when they brought the Ark of the Covenant, which had journeyed through...
The planned completion date of our entire building project was 14th April 2020. Our contractors had worked very hard during the winter period and as a result they were able to hand the building...
Work to the new annexe continued well over the winter and we were delighted to be informed that our completion date was Friday 21st February. This was two months ahead of schedule. We hope...
Work progressed well over the summer period with much concentration on the existing building. This meant that during the summer we only had use of the main church. In September the existing building was...
On Saturday 19th October 2019 Frank Sellar unveiled a Foundation Stone in part of our new building. You can watch the full ceremony below:
The building work has been helped by a mild winter allowing for good progress to be made. On the new annexe, the steelwork is erected and brick and block work up to the first...